GATE EE 2015 Set 1 — Question 51

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumEconomic Load DispatchEconomic Operation & CompensationPower Systems

Power Systems → Economic Operation & Compensation → Economic Load Dispatch

Last updated

Question

Consider the economic dispatch problem for a power plant having two generating units. The fuel costs in Rs/MWh along with the generation limits for the two units are given below:C1(P1)=0.01P12+30P1+10C_1(P_1) = 0.01 P_1^2 + 30 P_1 + 10 ; 100 MWP1150 MW100\text{ MW} \leq P_1 \leq 150\text{ MW}
C2(P2)=0.05P22+10P2+10C_2(P_2) = 0.05 P_2^2 + 10 P_2 + 10 ; 100 MWP2180 MW100\text{ MW} \leq P_2 \leq 180\text{ MW}The incremental cost (in Rs/MWh) of the power plant when it supplies 200 MW is ________.
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE EE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Economic Operation & Compensation