GATE EE 2021 Set 1 — Question 20

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
MCQ+1 / -0.33EasyEconomic Load DispatchEconomic Operation & CompensationPower Systems

Power Systems → Economic Operation & Compensation → Economic Load Dispatch

Last updated

Question

Two generators have cost functions F1F_1 and F2F_2. Their incremental-cost characteristics aredF1dP1=40+0.2P1\frac{dF_1}{dP_1} = 40 + 0.2P_1dF2dP2=32+0.4P2\frac{dF_2}{dP_2} = 32 + 0.4P_2They need to deliver a combined load of 260 MW. Ignoring the network losses, for economic operation, the generations P1P_1 and P2P_2 (in MW) are
Your answer

Choose one option, then check your answer.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE EE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Economic Operation & Compensation