Question

The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by
Plant 1: C1=350+6P1+0.004P12C_1 = 350 + 6P_1 + 0.004P_1^2
Plant 2: C2=450+aP2+0.003P22C_2 = 450 + aP_2 + 0.003P_2^2where P1P_1 and P2P_2 are power generated by plant 1 and plant 2, respectively, in MW and aa is constant. The incremental cost of power (λ\lambda) is 8 rupees per MWh. The two thermal power plants together meet a total power demand of 550 MW. The optimal generation of plant 1 and plant 2 in MW, respectively, are
Your answer

Choose one option, then check your answer.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE EE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Economic Operation & Compensation