P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days. R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project?
Correct answer
(C) 20:21
Solution
Let the total work be .
Work done by Q = .
Work done by R = .
1.Calculate the work rates of Q and R:
- Q can finish the task in .
- R can finish the task in .
2.Calculate the work done in 7 days from the start:
- Q took sick leave for the first 2 days, so Q worked for days.
Work done by Q = .
- R worked for all 7 days at 18 hours a day.
Work done by R = .
3.Find the ratio of work done by Q and R:
Ratio = .Therefore, the ratio is 20:21.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
Also appeared in
More questions on Quantitative Aptitude
2026 Set 1 Q1‘The team ____ more than 300 runs in 20 overs _________ rains. However, some players needed to…2026 Set 1 Q2If a positive real satisfies the following equation then…2026 Set 1 Q3The next figure (indicated by ‘?’) in the sequence is [figure]2026 Set 1 Q4‘All the mangoes in the basket are good.’ If the above statement is false, then which one of…2026 Set 1 Q5Consider the following statements about four numbers: (S1) The average of the four numbers is 25…