GATE ME 2026 Set 1 — Question 65

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumPERT & CPMOperations ResearchIndustrial Engineering

Industrial Engineering → Operations Research → PERT & CPM

Last updated

Question

The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (tot_o), most likely (tmt_m), and pessimistic (tpt_p) are given in the table below.
Activitytot_otmt_mtpt_p
1−22412
1−3246
1−43411
2−5369
3−42514
3−5333
4−53615
5−6258
The expected project length is ________ weeks (in integer).
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Operations Research