The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (), most likely (), and pessimistic () are given in the table below.
The expected project length is ________ weeks (in integer).
| Activity | |||
|---|---|---|---|
| 1−2 | 2 | 4 | 12 |
| 1−3 | 2 | 4 | 6 |
| 1−4 | 3 | 4 | 11 |
| 2−5 | 3 | 6 | 9 |
| 3−4 | 2 | 5 | 14 |
| 3−5 | 3 | 3 | 3 |
| 4−5 | 3 | 6 | 15 |
| 5−6 | 2 | 5 | 8 |
Correct answer
22 to 22
Solution
First, we calculate the expected time () for each activity using the formula :
- weeks
- weeks
- weeks
- weeks
- weeks
- weeks
- weeks
- weeks
1.Path 1-2-5-6: weeks
2.Path 1-3-5-6: weeks
3.Path 1-3-4-5-6: weeks
4.Path 1-4-5-6: weeks
The critical path is the longest path, which is 1-3-4-5-6 with a duration of 22 weeks. Therefore, the expected project length is 22 weeks.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Operations Research
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2025 Set 1 Q37Considering the actual demand and the forecast for a product given in the table below, the mean…