In general, the CORRECT sequence of surveying operations is
Correct answer
(C) Reconnaissance arrow Field observations arrow Data analysis arrow Map making
Solution
The standard sequence of operations in a surveying project is:
1.Reconnaissance: A preliminary inspection of the area to be surveyed to understand the terrain and plan the survey.
2.Field observations: The actual measurement of distances, angles, and elevations in the field.
3.Data analysis: Processing and calculating the observed data in the office.
4.Map making: Plotting the final results to create a map or plan.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Principles of Surveying
2026 Set 1 Q20The Whole Circle Bearing (WCB) of line is . The length of is 100 m. The…2026 Set 2 Q26Which one of the following statements is TRUE with respect to levelling survey?2026 Set 1 Q34A 30 m long tape is standardized at 25 C. It was used to measure the length of a line which…2026 Set 2 Q35A tourist visiting a city holds a map prepared at a scale of . The tourist measures the…2026 Set 1 Q35The height of the plane of collimation of a levelling instrument is 100.000 m from a datum. The…