A grit chamber of rectangular cross-section is to be designed to remove particles with diameter of and specific gravity of . The terminal settling velocity of the particles is estimated as . The chamber is having a width of and has to carry a peak wastewater flow of giving the depth of flow as . If a flow-through velocity of has to be maintained using a proportional weir at the outlet end of the chamber, the minimum length of the chamber (in , in integer) to remove particles completely is ____________
Correct answer
9 to 9
Solution
Given data:
Settling velocity,
Flow-through velocity,
Depth of flow, For complete removal of particles, the detention time must be equal to the settling time:The minimum length of the chamber is .
Settling velocity,
Flow-through velocity,
Depth of flow, For complete removal of particles, the detention time must be equal to the settling time:The minimum length of the chamber is .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Wastewater Treatment Processes
2026 Set 1 Q21A rapid sand filter bed of depth m has % porosity during service cycle. It is…2026 Set 1 Q22The settling velocity of inorganic particles in the sedimentation tank of a water treatment plant…2026 Set 1 Q25Which of the following components is/are NOT removed in the secondary treatment of sewage?2026 Set 2 Q27Column I presents common air pollutants, and column II presents treatment technologies commonly…2026 Set 2 Q28One-third of the solid matter in a sludge containing water is composed of fixed mineral…