GATE CE 2025 Set 2 — Question 25
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MSQ+1 / -0MediumWeirs on Permeable FoundationCanals & Hydraulic StructuresWater Resources EngineeringPipingSeepageGeotechnical Engineering
Geotechnical Engineering → Canals & Hydraulic Structures → Piping
Last updated
Question
Pick one or more CORRECT statement(s) from the choices given below, in the context of upstream and downstream cut-offs provided below the concrete apron of weirs / barrages constructed across alluvial rivers.
Correct answer
(B) Cut-offs are provided to increase the seepage length and prevent failure due to piping.; (C) The bottom level of cut-offs mainly depends on the scour depth.
Solution
Statement (A) is incorrect as cut-offs manage subsurface seepage, not surface flow rate. Statement (B) is correct as cut-offs increase the creep path (seepage length), reducing the exit gradient to prevent piping. Statement (C) is correct because cut-offs must extend below the maximum scour depth to ensure the structure's stability. Statement (D) is incorrect as the hydraulic jump is controlled by the stilling basin floor level and length, not the cut-offs themselves.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Canals & Hydraulic Structures
2026 Set 1 Q16Two reservoirs having different water levels are connected by two long parallel pipelines of same…2026 Set 1 Q17An irrigation canal is to be designed to deliver 10 cumec to meet the peak demand of 7500 hectare…2026 Set 1 Q18The name of a person in Column 1 is to be matched with the test mentioned in Column 2. | Column 1 |…2026 Set 2 Q19The Culturable Command Area (CCA) for a canal is 10000 hectares. The base period for a crop in the…2026 Set 2 Q20Following statements are made with respect to the mass curve of rainfall: (I) Slope at a point on…