GATE CS 2026 Set 2 — Question 51

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
MSQ+2 / -0HardSemaphoresProcess SynchronizationOperating System

Operating System → Process Synchronization → Semaphores

Last updated

Question

Consider three processes P1, P2, and P3 running identical code, as shown in the pseudocode below. A and B are two binary semaphores initialized to 1 and 0, respectively. X is a shared variable initialized to 0. Each line in the pseudocode is executed atomically.
Pseudocode of P1, P2, and P3
Wait(A);
Print(*);
X = X+1;
If (X == 2)
{
    Print($);
    Signal(B);
}
Signal(A);
Wait(B);
Print(#);
Signal(B);

Assume that any of the three processes can start to execute first and context switching can happen between these processes at any arbitrary time and in any arbitrary order.
Which of the following patterns is/are possible to be generated as an outcome of the execution of these three processes?
Your answer

Select all that apply, then check your answer.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CS question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Process Synchronization