The overcurrent relays for the line protection and loads connected at the buses are shown in the figure.
The relays are IDMT in nature having the characteristicThe maximum and minimum fault currents at bus B are 2000 A and 500 A respectively. Assuming the time multiplier setting and plug setting for relay to be 0.1 and 5A respectively, the operating time of (in seconds) is ____________

Correct answer
0.21 to 0.23
Solution
Relay is located on the line segment BC. The normal current through this line is the load at bus C, which is 100 A. Assuming the CT ratio for relay is based on this load, CT ratio = .For a fault current of 2000 A seen by the relay, the Plug Setting Multiplier (PSM) is:The operating time is calculated using the given characteristic:Thus, the operating time of relay is approximately 0.227 seconds.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE EE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Power System Protection
2026 Set 1 Q18Consider a power system with buses, of which are generator buses and the remaining are…2026 Set 1 Q19The initial three-phase voltage phasors (, , and ) at a bus of a…2026 Set 1 Q39In the circuit shown, the phase currents are A…2026 Set 1 Q40The operating characteristic of a reactance relay is given by , where is the…2026 Set 1 Q41A three-phase two-winding transformer has a voltage transformation ratio…