Question
Base load power plants areP: wind farms.
Q: run-of-river plants.
R: nuclear power plants.
S: diesel power plants.
Q: run-of-river plants.
R: nuclear power plants.
S: diesel power plants.
Correct answer
(D) Q and R only
Solution
Base load power plants are those that provide a steady flow of power to meet the minimum demand of the grid throughout the day.
- Nuclear power plants (R) are ideal for base load because they have high capital costs and low operating costs, and they are difficult to ramp up or down quickly.
- Run-of-river hydroelectric plants (Q) are also considered base load because they utilize the continuous flow of a river and typically lack significant storage capacity to vary output for peak loads.
- Wind farms (P) are intermittent and unpredictable, making them unsuitable for base load without massive storage.
- Diesel power plants (S) have high fuel costs and are generally used for peak loads or emergency backup.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE EE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Generation & Transmission
2026 Set 1 Q18Consider a power system with buses, of which are generator buses and the remaining are…2026 Set 1 Q19The initial three-phase voltage phasors (, , and ) at a bus of a…2026 Set 1 Q39In the circuit shown, the phase currents are A…2026 Set 1 Q40The operating characteristic of a reactance relay is given by , where is the…2026 Set 1 Q41A three-phase two-winding transformer has a voltage transformation ratio…