Question
Consider the following network of activities, with each activity named A-L, illustrated in the nodes of the network.
The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is ______ hours.

Correct answer
2 to 2
Solution
To find the slack on activity L, we first find the critical path and its duration.
Possible paths from START to FINISH:
Slack on activity L = hours.
Possible paths from START to FINISH:
1.A-B-C-F-I-J-K: hours
2.A-B-C-E-K: hours
3.A-B-C-D-G-H-L: hours
The critical path is A-B-C-F-I-J-K with duration hours.Slack on activity L = hours.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Operations Research
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…