GATE ME 2020 Set 2 — Question 33

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+1 / -0MediumPERT & CPMOperations ResearchIndustrial Engineering

Industrial Engineering → Operations Research → PERT & CPM

Last updated

Question

Consider the following network of activities, with each activity named A-L, illustrated in the nodes of the network.
Network diagram showing activities A through L with durations
The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is ______ hours.
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Operations Research