GATE ME 2021 Set 2 — Question 39
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MCQ+2 / -0.67MediumAggregate Production PlanningProduction Planning & ControlIndustrial Engineering
Industrial Engineering → Production Planning & Control → Aggregate Production Planning
Last updated
Question
A factory produces products, each of which requires processing on workstations. Let be the amount of processing time that one unit of the product requires on the workstation. Let the revenue from selling one unit of the product be and be the holding cost per unit per time period for the product. The planning horizon consists of time periods. The minimum demand that must be satisfied in time period is , and the capacity of the workstation in time period is . Consider the aggregate planning formulation below, with decision variables (amount of product sold in time period ), (amount of product manufactured in time period ) and (amount of product held in inventory at the end of time period ).subject to
< capacity constraint >
< inventory balance constraint >
The capacity constraints and inventory balance constraints for this formulation are
< capacity constraint >
< inventory balance constraint >
The capacity constraints and inventory balance constraints for this formulation are
Correct answer
(A) Σᵢ₌₁^(m) aᵢⱼ Xᵢₜ ≤ cⱼₜ ∀ j, t and Iᵢₜ = I_(i,t-1) + Xᵢₜ - Sᵢₜ ∀ i, t
Solution
1.Capacity Constraint: For each workstation in each time period , the total processing time required for all products manufactured () must not exceed the available capacity . The time required for product on workstation is . Summing over all products : .
2.Inventory Balance Constraint: For each product in each time period , the inventory at the end of the period () equals the inventory from the previous period () plus the amount manufactured in the current period () minus the amount sold in the current period (): .
Comparing with the options, Option (A) matches both constraints.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Production Planning & Control
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…