GATE ME 2025 Set 1 — Question 65

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumPERT & CPMOperations ResearchIndustrial Engineering

Industrial Engineering → Operations Research → PERT & CPM

Last updated

Question

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is _____ hours (answer in integer).
ActivityImmediate predecessorDuration (hours)
A-4
BA8
CA5
DB2
EB7
FC6
GD3
HE, F, G9
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Operations Research