GATE CE 2014 Set 2 — Question 63
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.NAT+2 / -0MediumSignal Design (Webster's)Intersections & SignalsTransportation Engineering
Transportation Engineering → Intersections & Signals → Signal Design (Webster's)
Last updated
Question
A pre-timed four phase signal has critical lane flow rate for the first three phases as 200, 187 and 210 veh/hr with saturation flow rate of 1800 veh/hr/lane for all phases. The lost time is given as 4 seconds for each phase. If the cycle length is 60 seconds, the effective green time (in seconds) of the fourth phase is ______________
Correct answer
14 to 18
Solution
Given:
Using Webster's formula for optimum cycle length:
Total critical flow ratio
Effective green time for the fourth phase ():
seconds.
- Cycle length s
- Number of phases
- Lost time per phase s
- Total lost time s
- Saturation flow rate veh/hr/lane
- Critical lane flow rates: , , veh/hr
Using Webster's formula for optimum cycle length:
Total critical flow ratio
Effective green time for the fourth phase ():
seconds.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Intersections & Signals
2026 Set 1 Q19Corrections are applied to the basic length of the runway strip considering: (i) The elevation …2026 Set 2 Q23An incident occurred on one side of a median on a four-lane dual carriageway road section. This…2026 Set 2 Q24Which one of the following statements is TRUE?2026 Set 1 Q24Cant on a Broad Gauge railway track is calculated for an equilibrium speed (in km/h),…2026 Set 2 Q25The primary purpose of the Windrose diagram is for the design of