GATE CE 2016 Set 2 — Question 32
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MCQ+1 / -0.33MediumTraffic Load & ESALPavement DesignTransportation Engineering
Transportation Engineering → Pavement Design → Traffic Load & ESAL
Last updated
Question
If the total number of commercial vehicles per day ranges from 3000 to 6000, the minimum percentage of commercial traffic to be surveyed for axle load is
Correct answer
(A) 15
Solution
According to IRC:37-2012 (Guidelines for the Design of Flexible Pavements), the minimum sample size for axle load surveys depends on the commercial vehicles per day (CVPD). For a traffic volume ranging from 3000 to 6000 CVPD, the recommended minimum sample size is 15%.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Pavement Design
2026 Set 1 Q19Corrections are applied to the basic length of the runway strip considering: (i) The elevation …2026 Set 2 Q23An incident occurred on one side of a median on a four-lane dual carriageway road section. This…2026 Set 2 Q24Which one of the following statements is TRUE?2026 Set 1 Q24Cant on a Broad Gauge railway track is calculated for an equilibrium speed (in km/h),…2026 Set 2 Q25The primary purpose of the Windrose diagram is for the design of