A triangular pipe network is shown in the figure.
The head loss in each pipe is given by , with the variables expressed in a consistent set of units. The value of for the pipe is 1 and for the pipe is 2. If the discharge supplied at the point (i.e., 100) is equally divided between the pipes and , the value of (up to two decimal places) for the pipe should be ___________

Correct answer
0.6 to 0.63
Solution
Given:
at node A.
(equally divided).Applying continuity at node B:
(flow is from C to B).Applying continuity at node C:
. (Consistent).For a closed loop ABC, the sum of head losses must be zero (). Taking clockwise as positive:
Rounding to two decimal places, .
at node A.
(equally divided).Applying continuity at node B:
(flow is from C to B).Applying continuity at node C:
. (Consistent).For a closed loop ABC, the sum of head losses must be zero (). Taking clockwise as positive:
Rounding to two decimal places, .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Pipe Flow
2026 Set 1 Q16Two reservoirs having different water levels are connected by two long parallel pipelines of same…2026 Set 1 Q17An irrigation canal is to be designed to deliver 10 cumec to meet the peak demand of 7500 hectare…2026 Set 2 Q19The Culturable Command Area (CCA) for a canal is 10000 hectares. The base period for a crop in the…2026 Set 2 Q20Following statements are made with respect to the mass curve of rainfall: (I) Slope at a point on…2026 Set 1 Q23Gradually Varied Flow (GVF) profiles in open channels given in Column 1 are to be matched with the…