Tie bars of diameter are to be provided in a concrete pavement slab. The working tensile stress of the tie bars is , the average bond strength between a tie bar and concrete is , and the joint gap between the slabs is . Ignoring the loss of bond and the tolerance factor, the design length of the tie bars (in mm, round off to the nearest integer) is ________
Correct answer
700 to 700
Solution
The total length of a tie bar () is the sum of the development lengths required on both sides of the joint plus the width of the joint gap.The development length () is given by:Where:
(diameter of bar)
(working tensile stress)
(average bond strength)Total length
Substituting the values:The design length of the tie bars is .
(diameter of bar)
(working tensile stress)
(average bond strength)Total length
Substituting the values:The design length of the tie bars is .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Pavement Design
2026 Set 1 Q19Corrections are applied to the basic length of the runway strip considering: (i) The elevation …2026 Set 2 Q23An incident occurred on one side of a median on a four-lane dual carriageway road section. This…2026 Set 2 Q24Which one of the following statements is TRUE?2026 Set 1 Q24Cant on a Broad Gauge railway track is calculated for an equilibrium speed (in km/h),…2026 Set 2 Q25The primary purpose of the Windrose diagram is for the design of