GATE CE 2019 Set 2 — Question 24

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
MCQ+1 / -0.33EasyFlood RoutingHydrographs & GroundwaterWater Resources Engineering

Water Resources Engineering → Hydrographs & Groundwater → Flood Routing

Last updated

Question

An inflow hydrograph is routed through a reservoir to produce an outflow hydrograph. The peak flow of the inflow hydrograph is PIP_I and the time of occurrence of the peak is tIt_I. The peak flow of the outflow hydrograph is POP_O and the time of occurrence of the peak is tOt_O. Which one of the following statements is correct?
Your answer

Choose one option, then check your answer.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Hydrographs & Groundwater