Three reservoirs P, Q, and R are interconnected by pipes as shown in the figure (not drawn to the scale). Piezometric head at the junction S of the pipes is . Assume acceleration due to gravity as and density of water as . The length of the pipe from junction S to the inlet of reservoir R is .
Considering head loss only due to friction (with friction factor of for all the pipes), the height of water level in the lowermost reservoir R (in m, round off to one decimal place) with respect to the datum, is ___________.

Correct answer
97.2 to 97.8
Solution
1.Piezometric head at junction S, .
2.For pipe SR: Length , Diameter , Friction factor .
3.By continuity at junction S, the flow into the junction must equal the flow out: .
4.Flow from P to S: .
5.Flow from Q to S: .
6.Total flow to R: .
7.Velocity in pipe SR: .
8.Head loss in pipe SR due to friction: .
9.Piezometric head at reservoir R: .
10.Rounding to one decimal place, the height is .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Pipe Flow
2026 Set 1 Q16Two reservoirs having different water levels are connected by two long parallel pipelines of same…2026 Set 1 Q17An irrigation canal is to be designed to deliver 10 cumec to meet the peak demand of 7500 hectare…2026 Set 2 Q19The Culturable Command Area (CCA) for a canal is 10000 hectares. The base period for a crop in the…2026 Set 2 Q20Following statements are made with respect to the mass curve of rainfall: (I) Slope at a point on…2026 Set 1 Q23Gradually Varied Flow (GVF) profiles in open channels given in Column 1 are to be matched with the…