Question
A two-hour duration storm event with uniform excess rainfall of 3 cm occurred on a watershed. The ordinates of streamflow hydrograph resulting from this event are given in the table.
Considering a constant baseflow of 10 m/s, the peak flow ordinate (in m/s) of one-hour unit hydrograph for the watershed is ________ . (in integer)
| Time (hours) | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|---|
| Streamflow () | 10 | 16 | 34 | 40 | 31 | 25 | 16 | 10 |
Correct answer
12 to 12
Solution
1.Calculate Direct Runoff Hydrograph (DRH) by subtracting baseflow ():
DRH ordinates: (at hours)2.This DRH is for excess rainfall in .
ordinates (divide DRH by ):3.Use S-curve method to find :
-curve ordinates :Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Hydrographs & Groundwater
2026 Set 1 Q16Two reservoirs having different water levels are connected by two long parallel pipelines of same…2026 Set 1 Q17An irrigation canal is to be designed to deliver 10 cumec to meet the peak demand of 7500 hectare…2026 Set 2 Q19The Culturable Command Area (CCA) for a canal is 10000 hectares. The base period for a crop in the…2026 Set 2 Q20Following statements are made with respect to the mass curve of rainfall: (I) Slope at a point on…2026 Set 1 Q23Gradually Varied Flow (GVF) profiles in open channels given in Column 1 are to be matched with the…