GATE CE 2022 Set 1 — Question 62

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumTraffic SignalsIntersections & SignalsTransportation Engineering

Transportation Engineering → Intersections & Signals → Traffic Signals

Last updated

Question

A two-phase signalized intersection is designed with a cycle time of 100 s100 \text{ s}. The amber and red times for each phase are 4 s4 \text{ s} and 50 s50 \text{ s}, respectively. If the total lost time per phase due to start-up and clearance is 2 s2 \text{ s}, the effective green time of each phase is ______s. (in integer)
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Intersections & Signals