An Activated Sludge Process (ASP) has an inlet wastewater flowrate of with a Biochemical Oxygen Demand (BOD) concentration of . It produces treated wastewater containing BOD. The aeration tank has a working volume of and a biomass concentration of . Biological Sludge Residence Time (BSRT) of the system is . The influent wastewater and the treated effluent from the system have negligible concentrations of biomass. The sludge recycle line from the bottom of the Secondary Sedimentation Tank (SST) to the inlet of the aeration tank has a flowrate of .To maintain equilibrium, the flowrate (in ) of sludge that is to be wasted from the system is ______ (in integer).
Correct answer
230 to 250
Solution
Given:
Inlet flowrate,
Aeration tank volume,
Biomass concentration in aeration tank,
BSRT,
Recycle flowrate,
Effluent biomass concentration, Assuming wasting is from the recycle line, let be the waste flowrate and be the biomass concentration in the recycle line.
Mass balance on biomass for the system:Since :Mass balance on biomass around the Secondary Sedimentation Tank (SST):Substitute into the equation:
Inlet flowrate,
Aeration tank volume,
Biomass concentration in aeration tank,
BSRT,
Recycle flowrate,
Effluent biomass concentration, Assuming wasting is from the recycle line, let be the waste flowrate and be the biomass concentration in the recycle line.
Mass balance on biomass for the system:Since :Mass balance on biomass around the Secondary Sedimentation Tank (SST):Substitute into the equation:
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Wastewater Treatment Processes
2026 Set 1 Q21A rapid sand filter bed of depth m has % porosity during service cycle. It is…2026 Set 1 Q22The settling velocity of inorganic particles in the sedimentation tank of a water treatment plant…2026 Set 1 Q25Which of the following components is/are NOT removed in the secondary treatment of sewage?2026 Set 2 Q27Column I presents common air pollutants, and column II presents treatment technologies commonly…2026 Set 2 Q28One-third of the solid matter in a sludge containing water is composed of fixed mineral…