GATE CE 2026 Set 1 — Question 65

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumSedimentationDrinking Water TreatmentEnvironmental Engineering

Environmental Engineering → Drinking Water Treatment → Sedimentation

Last updated

Question

The maximum demand at a water purification plant has been estimated as 12 million litres per day. For the raw supplies, a rectangular sedimentation tank is to be designed with mechanical sludge removal arrangement. Consider depth of the tank as 4 m, detention period as 6 hours, and velocity of flow as 0.003 m/s.
The width (in m) of the detention tank is _________ (rounded off to two decimal places).
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Drinking Water Treatment