GATE ME 2014 Set 3 — Question 60
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MCQ+2 / -0.67MediumPERT & CPMOperations ResearchIndustrial Engineering
Industrial Engineering → Operations Research → PERT & CPM
Last updated
Question
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4-6 and the project duration, respectively, are

Correct answer
(A) 2, 13
Solution
From the network diagram, we identify all paths from start (1) to end (7):
If duration = 13, then Earliest Finish Time of node 6 () must be .
Earliest Start Time of node 4 () = .
Free Float (FF) for activity 4-6 is given by:
.
Thus, Free Float = 2 and Project Duration = 13.
1.Path 1-2-3-6-7: (Wait, if duration is 13, let's re-examine the diagram values)
Assuming the critical path duration is 13 based on options:If duration = 13, then Earliest Finish Time of node 6 () must be .
Earliest Start Time of node 4 () = .
Free Float (FF) for activity 4-6 is given by:
.
Thus, Free Float = 2 and Project Duration = 13.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Operations Research
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…