GATE ME 2014 Set 4 — Question 61
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.NAT+2 / -0MediumQueuing Models (M/M/1)Operations ResearchIndustrial Engineering
Industrial Engineering → Operations Research → Queuing Models (M/M/1)
Last updated
Question
At a work station, 5 jobs arrive every minute. The mean time spent on each job in the work station is 1/8 minute. The mean steady state number of jobs in the system is __________
Correct answer
1.62 to 1.7
Solution
The problem describes a queuing system. We are given:
jobs/minute.This scenario can be modeled as a simple M/M/1 queuing system, assuming Poisson arrivals and exponential service times, which is standard for such problems unless specified otherwise.The question asks for the mean steady state number of jobs in the system, denoted by .The formula for the mean number of jobs in the system in an M/M/1 queue is:For this formula to be valid, the system must be stable, which means the traffic intensity must be less than 1.
In this case, , so the system is stable and a steady state exists.Now, we can substitute the values of and into the formula for :Calculating the numerical value:This value falls within the specified answer range of 1.62 to 1.70.
- The arrival rate of jobs, jobs/minute.
- The mean time spent on each job (service time), minute/job.
jobs/minute.This scenario can be modeled as a simple M/M/1 queuing system, assuming Poisson arrivals and exponential service times, which is standard for such problems unless specified otherwise.The question asks for the mean steady state number of jobs in the system, denoted by .The formula for the mean number of jobs in the system in an M/M/1 queue is:For this formula to be valid, the system must be stable, which means the traffic intensity must be less than 1.
In this case, , so the system is stable and a steady state exists.Now, we can substitute the values of and into the formula for :Calculating the numerical value:This value falls within the specified answer range of 1.62 to 1.70.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Operations Research
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…