The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities and , respectively, are
| Activity | Predecessors | Duration (days) |
|---|---|---|
| a | - | 2 |
| b | - | 4 |
| c | a | 2 |
| d | b | 3 |
| e | c | 2 |
| f | c | 4 |
| g | d, e | 5 |
Correct answer
(B) 1 and 4
Solution
1.Identify all paths and their durations:
- Path 1: a-c-e-g days
- Path 2: a-c-f days
- Path 3: b-d-g days (Critical Path)
3.Calculate Total Float ():
- For activity :
day
- For activity :
(end of project)
daysThus, the total floats are 1 and 4 respectively.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Operations Research
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…