GATE ME 2015 Set 1 — Question 53

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
MCQ+2 / -0.67EasyPERT & CPMOperations ResearchIndustrial Engineering

Industrial Engineering → Operations Research → PERT & CPM

Last updated

Question

Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.
ActivityDuration (days)
1-22
2-31
4-33
1-43
2-53
3-52
4-54
The critical path (CP) in the network is
Your answer

Choose one option, then check your answer.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

Also appeared in

More questions on Operations Research