Following data refers to the jobs (P, Q, R, S) which have arrived at a machine for scheduling. The shortest possible average flow time is ________ days.
| Job | Processing Time (days) |
|---|---|
| P | 15 |
| Q | 9 |
| R | 22 |
| S | 12 |
Correct answer
31 to 31
Solution
To minimize the average flow time, the Shortest Processing Time (SPT) rule is applied.
Total Flow Time = days
1.Sort the jobs in increasing order of their processing times:
- Job Q: 9 days
- Job S: 12 days
- Job P: 15 days
- Job R: 22 days
- Flow time of Q = 9
- Flow time of S = 9 + 12 = 21
- Flow time of P = 21 + 15 = 36
- Flow time of R = 36 + 22 = 58
Total Flow Time = days
4.Calculate the average flow time:
Average Flow Time = days.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE ME question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Production Planning & Control
2026 Set 1 Q46An objective function of primal variables ( and ) is described below: Minimize…2026 Set 1 Q47Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due…2026 Set 1 Q60The actual demand for castings in a factory is units and units for the months of…2026 Set 1 Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order…2026 Set 1 Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e.,…