Question
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
| Activity | Duration (days) | Activity | Duration (days) |
|---|---|---|---|
| A Inauguration | 1 | G Flooring | 25 |
| B Foundation work | 7 | H Electrification | 7 |
| C Structural construction-1 | 30 | I Plumbing | 7 |
| D Structural construction-2 | 30 | J Wood work | 7 |
| E Brick masonry work | 25 | K Coloring | 3 |
| F Plastering | 7 | L Handing over function | 1 |

Correct answer
(C) 0 and 0
Solution
To find the total float, we first identify the critical path(s) of the network. The duration of various paths from node 1 to node 12 are:
1.Path 1-2-3-4-6-8-10-11-12: days.
2.Path 1-2-3-5-7-9-10-11-12: days.
3.Path 1-2-3-4-5-7-9-10-11-12 (via dummy 4-5): days.
Since the maximum duration is 81 days, all these paths are critical paths. Activity 5-7 (G) lies on Path 2 and Path 3, which are critical. Activity 11-12 (L) lies on all critical paths. The total float for any activity on a critical path is 0. Therefore, the total floats for activities 5-7 and 11-12 are 0 and 0, respectively.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…