GATE CE 2017 Set 2 — Question 21

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+1 / -0MediumFlow NetsSeepageGeotechnical Engineering

Geotechnical Engineering → Seepage → Flow Nets

Last updated

Question

A sheet pile has an embedment depth of 12 m12 \text{ m} in a homogeneous soil stratum. The coefficient of permeability of soil is 106 m/s10^{-6} \text{ m/s}. Difference in the water levels between the two sides of the sheet pile is 4 m4 \text{ m}. The flow net is constructed with five number of flow lines and eleven number of equipotential lines. The quantity of seepage (in cm3/s\text{cm}^3/\text{s} per m, up to one decimal place) under the sheet pile is ________________
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Seepage