Question
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is per day.
If the project is targeted for completion in 16 days, the total cost (in ) to be incurred by the contractor would be ______

| Activity | Normal Duration (days) | Crash Duration (days) | Normal Cost (INR) | Crash Cost (INR) |
|---|---|---|---|---|
| P | 6 | 4 | 15000 | 25000 |
| Q | 5 | 2 | 6000 | 12000 |
| R | 5 | 3 | 8000 | 9500 |
| S | 6 | 3 | 7000 | 10000 |
| T | 3 | 2 | 6000 | 9000 |
| U | 2 | 1 | 4000 | 6000 |
| V | 4 | 2 | 20000 | 28000 |
Correct answer
149500 to 149500
Solution
1.Calculate Cost Slopes for each activity:
Cost Slope = - /day
- /day
- /day
- /day
- /day
- /day
- /day
- Path 1: days
- Path 2: days
- Path 3: days (Critical Path)
3.Crash to 16 days:
- Step 1 (18 to 17 days): Crash critical path . Cheapest is (750/day). Crash by 1 day. Cost increase = 750. New durations: Path 1 = 17, Path 2 = 16, Path 3 = 17. Now Path 1 and Path 3 are critical.
- Step 2 (17 to 16 days): Crash both Path 1 and Path 3. Options: Crash (5000), (4000), or . Cheapest is or at . Crash by 1 more day (limit reached) and by 1 day. Cost increase = 2750. New durations: Path 1 = 16, Path 2 = 16, Path 3 = 16.
- Total Normal Direct Cost =
- Total Crash Cost =
- Total Indirect Cost for 16 days =
- Total Project Cost = .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…