GATE CE 2020 Set 2 — Question 19
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MCQ+1 / -0.33EasySaturation FlowIntersections & SignalsTransportation Engineering
Transportation Engineering → Intersections & Signals → Saturation Flow
Last updated
Question
The traffic starts discharging from an approach at an intersection with the signal turning green. The constant headway considered from the fourth or fifth headway position is referred to as
Correct answer
(D) saturation headway
Solution
Saturation headway is the constant average headway achieved by a queue of vehicles discharging from an intersection after the initial startup lost time (usually after the 4th or 5th vehicle). It represents the minimum average time between successive vehicles under saturated flow conditions.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Intersections & Signals
2026 Set 1 Q19Corrections are applied to the basic length of the runway strip considering: (i) The elevation …2026 Set 2 Q23An incident occurred on one side of a median on a four-lane dual carriageway road section. This…2026 Set 2 Q24Which one of the following statements is TRUE?2026 Set 1 Q24Cant on a Broad Gauge railway track is calculated for an equilibrium speed (in km/h),…2026 Set 2 Q25The primary purpose of the Windrose diagram is for the design of