GATE CE 2020 Set 2 — Question 31
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.NAT+1 / -0MediumTraffic Volume StudiesTraffic Studies & FlowTransportation Engineering
Transportation Engineering → Traffic Studies & Flow → Traffic Volume Studies
Last updated
Question
traffic count at a road section was observed to be vehicles on a Tuesday in the month of July. If daily adjustment factor for Tuesday is and monthly adjustment factor for July is , the Annual Average Daily Traffic (in veh/day, round off to the nearest integer) is ________.
Correct answer
1021 to 1024
Solution
The Annual Average Daily Traffic (AADT) is calculated by multiplying the observed traffic count by the daily and monthly adjustment factors:Given:
- Traffic Count
- Daily Adjustment Factor (Tuesday)
- Monthly Adjustment Factor (July)
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Traffic Studies & Flow
2026 Set 1 Q19Corrections are applied to the basic length of the runway strip considering: (i) The elevation …2026 Set 2 Q23An incident occurred on one side of a median on a four-lane dual carriageway road section. This…2026 Set 2 Q24Which one of the following statements is TRUE?2026 Set 1 Q24Cant on a Broad Gauge railway track is calculated for an equilibrium speed (in km/h),…2026 Set 2 Q25The primary purpose of the Windrose diagram is for the design of