GATE CE 2021 Set 2 — Question 52

Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.
NAT+2 / -0MediumCPMConstruction ManagementStructural EngineeringCritical Path

Structural Engineering → Construction Management → CPM

Last updated

Question

The activity details for a small project are given in the Table.
ActivityDuration (days)Depends on
A6-
B10A
C14A
D8B
E12C
F8C
G16D, E
H8F, G
K2B
L5G, K
The total time (in days, in integer) for project completion is ________
Your answer

Enter a number. Decimals, negative values and scientific notation are accepted.

The solution stays hidden until you check.

Continue learning with Success Tracker

A step still unclear? Work through it with support

Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.

AI-powered practice· Unlimited practice on eligible plans
PYQs with solutions
Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
Practice that adapts
Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
AI doubt support
Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.

Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.

This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.

More questions on Construction Management