GATE CE 2024 Set 2 — Question 52
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.NAT+2 / -0MediumCritical PathConstruction ManagementStructural Engineering
Structural Engineering → Construction Management → Critical Path
Last updated
Question
The table shows the activities and their durations and dependencies in a project.
The total duration (in days) of the project is___________ (in integer).
| Activity | Duration (Days) | Depends on |
|---|---|---|
| A | 8 | - |
| B | 4 | A |
| C | 4 | B |
| D | 4 | C, L |
| F | 4 | A |
| G | 4 | F |
| H | 6 | G, L |
| K | 10 | A |
| L | 6 | F, K |
Correct answer
30 to 30
Solution
We calculate the Earliest Finish (EF) for each activity based on dependencies:
Duration = max(EF(D), EF(H)) = max(28, 30) = 30 days.
- A: EF = 8
- B: EF = EF(A) + 4 = 8 + 4 = 12
- C: EF = EF(B) + 4 = 12 + 4 = 16
- F: EF = EF(A) + 4 = 8 + 4 = 12
- G: EF = EF(F) + 4 = 12 + 4 = 16
- K: EF = EF(A) + 10 = 8 + 10 = 18
- L: EF = max(EF(F), EF(K)) + 6 = max(12, 18) + 6 = 18 + 6 = 24
- D: EF = max(EF(C), EF(L)) + 4 = max(16, 24) + 4 = 24 + 4 = 28
- H: EF = max(EF(G), EF(L)) + 6 = max(16, 24) + 6 = 24 + 6 = 30
Duration = max(EF(D), EF(H)) = max(28, 30) = 30 days.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…