GATE CE 2016 Set 1 — Question 49
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.NAT+2 / -0EasyPERTConstruction ManagementStructural Engineering
Structural Engineering → Construction Management → PERT
Last updated
Question
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.
The expected completion time (in days) of the project is _________

Correct answer
37 to 38
Solution
In PERT (Program Evaluation and Review Technique), the expected time () for an activity is calculated using the formula:where:
- = Optimistic time
- = Most likely time
- = Pessimistic time
1.For activity E-F (8-10-14):
2.For activity F-G (6-8-11):
3.For activity G-H (5-7-10):
4.For activity H-I (7-12-18):
The total expected completion time of the project () is the sum of the expected times of all activities on the critical path:Thus, the expected completion time is approximately 37.83 days, which falls within the range of 37 to 38.Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…