GATE CE 2024 Set 1 — Question 16
Go beyond PYQs with Success TrackerAI-powered personalised practice and doubt support. Unlimited practice on eligible plans; AI usage limits apply.MCQ+1 / -0.33MediumCost EstimationConstruction ManagementStructural Engineering
Structural Engineering → Construction Management → Cost Estimation
Last updated
Question
Consider the statements and .P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.Which one of the following options is CORRECT?
Correct answer
(A) Both P and Q are TRUE
Solution
Statement P is TRUE: A preliminary estimate (also known as an approximate or rough estimate) is prepared during the early stages of a project to obtain administrative approval and to allocate funds (budgeting). It is typically finalized towards the end of the planning and design phase to set the project budget.Statement Q is TRUE: A detailed estimate is prepared after the design and drawings are finalized. It provides a precise cost breakdown and is used for tendering, contract management, and as a baseline for controlling costs during the actual execution of the project.Since both statements are accurate descriptions of the respective estimates, option (A) is correct.
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…