The following figure shows the arrangement of formwork for casting a cantilever RC beam.
The correct sequence of removing the Shores/Props is

Correct answer
(B) S5 arrow S4 arrow S3 arrow S2 arrow S1
Solution
For a cantilever beam, the props should be removed starting from the free end and moving towards the fixed support. This ensures that the beam gradually takes up its own weight as a cantilever without inducing unexpected stresses or cracking. In the given figure, is at the free end and is closest to the fixed support (RC Column). Therefore, the correct sequence is .
Continue learning with Success Tracker
A step still unclear? Work through it with support
Use Success Tracker to ask about the reasoning, then try another GATE CE question to check your understanding.
AI-powered practice· Unlimited practice on eligible plans
- PYQs with solutions
- Attempt available previous-year questions, then compare your reasoning with the worked solution. Coverage varies by stream.
- Practice that adapts
- Choose a topic, work on weaker areas and bookmark questions to revisit. Your attempts feed your progress tracking.
- AI doubt support
- Ask follow-up questions about a step or concept while practising, instead of stopping at the final answer.
Unlimited practice is available on eligible plans. Free practice and AI usage have limits; check the current plan allowances before choosing.
This page stays readable without an account. AI responses can be wrong; check them against the solution and source material.
More questions on Construction Management
2026 Set 1 Q13A thin-walled spherical gas balloon of radius and wall thickness () is subjected…2026 Set 2 Q14A rectangular singly reinforced concrete beam has a width of 300 mm and an effective depth of 550…2026 Set 1 Q14Black dot shown in the figure qualitatively represents the shear centre of the angle section. The…2026 Set 1 Q15Which one of the following is utilized to determine the long-term deformation of concrete under…2026 Set 2 Q15As per IS:800-2007, design of a cantilever steel beam section for its moment capacity requires…